← All stories
Roma's New Stadium: Construction to Begin March 2027
·29 September 2026·5h ago

Roma's New Stadium: Construction to Begin March 2027

Source: Il Messaggero – Roma

Roma have cleared a historic hurdle in their plan to build a new stadium at Pietralata after winning approval for the definitive project on 28 September. The stadium design is now locked in place: a structure with over 60,000 capacity, two green parks, three pedestrian and cycle paths, car and motorcycle parking, bike facilities, and public transport improvements. No further modifications can be requested, and the blueprint cannot change.

The timing is critical because Roma must meet a UEFA deadline to keep Pietralata in contention as a host venue for Euro 2032. The stadium must be "construction-ready" by March 2027, meaning all planning processes must be complete and work can begin in theory. Recent stadium law reforms and the appointment of extraordinary commissioner Massimo Sessa, president of the Supreme Council for Public Works, have accelerated the process significantly. Roma have already secured the urban planning variant approval, completed the convention text (the future contract between the developer and the council), and concluded expropriations at the normative level. The remaining work centres on preparing the executive project—the final technical drawings specifying every detail down to "the measurements and type of screws needed to fix door handles to changing room doors," as the article explains. Roma's officials expect this to be submitted around the new year, roughly four months from now, though architects and engineers are already working toward an ambitious goal of completing it before Christmas, once final permits come through between July and August.

Once Roma deposit the executive project, Sessa will deploy his special powers to immediately publish the tender for the construction contract. Before the actual procurement begins, a "verification and validation" phase must occur: all offices that issued binding conditions—such as Roma Natura's requirement that 50 per cent of newly planted trees be oaks—must confirm these requirements appear in the final project drawings. The Project Manager will then validate that the work meets all conditions and is ready to begin. These two steps should take only days under commissarial powers. A European tender will then be opened, though it is difficult to predict significant competition for a €1.3 billion project (including VAT) of such complexity; if only Roma enters the bid, the winner will be confirmed within days.

After those preliminary steps, only final acts remain: signing the convention, submitting insurance policies as required by law, and issuing the building permit. Roma must also complete archaeological excavations before construction proper can start.

● AI Generated Summary

This summary was generated by an AI model. Always read the source for complete and accurate information.

Story Coverage6 sources on this story

AS Roma has cleared the decisive regulatory hurdle for its new Pietralata stadium. On 28 September, the Services Conference concluded with a unanimous favourable opinion, and Extraordinary Commissioner Massimo Sessa issued the single authorization for construction. The project now moves from the approval phase into the operational phase, with groundbreaking targeted for March 2027. The stadium design is locked in place and cannot be modified further—a critical requirement to keep Pietralata in contention as a host venue for Euro 2032. The facility will hold 60,605 spectators, including approximately 23,000 seats in the South Curve, and encompasses green parks, pedestrian and cycle paths, parking, and public transport improvements.

Roma and the Friedkin Group must now develop a detailed executive project that incorporates all requirements emerging from the Services Conference, including archaeology, environment, traffic and public works provisions. Il Messaggero reports this stage is expected to take three to four months, with Roma's officials aiming to submit the project around the new year, though architects are working toward completion before Christmas. Parallel to design work, the municipal administration will handle project verification, a public concession procedure following public-private partnership rules, and expropriations of private land now possible following the public utility declaration. Il Messaggero describes the subsequent verification and validation phase—where all issuing offices confirm their requirements appear in final drawings—as taking only days under commissarial powers.

Sessa has accelerated processes significantly. Il Messaggero notes that once Roma deposits the executive project, Sessa will immediately publish a European tender for the construction contract, with a €1.3 billion budget (including VAT). The mayor's schedule projects construction taking approximately two and a half years, with potential completion by the end of 2029 or 2031 depending on the outlet. Forza Roma highlights the financial significance: projected stadium revenue of €153 million in 2031—a 245 per cent increase from the €44.4 million currently earned at the Olimpico—could raise Roma's overall revenues by 60 per cent, positioning the club among Europe's elite earners.

AI synthesis of all sources below — always check the originals.

Testo Originale / Source Text

“Concluso un iter - quello approvativo - se ne apre subito un altro, quello per arrivare alle ruspe, alle gru e agli operai in azione. Per il progetto della Roma di realizzare lo stadio a Pietralata ieri è stata una giornata storica: via libera al progetto definitivo. Quindi, di fatto, da ieri non…”

Read the full article in Italian at Il Messaggero – Roma.

Read original on Il Messaggero – Roma →

More Club News

Roma Receive Final Approval for New Pietralata Stadium Project
Club News● AI
1h ago

Roma Receive Final Approval for New Pietralata Stadium Project

AS Roma have secured definitive authorization to build a new stadium in the Pietralata area following approval by the services' conference on Tuesday at the Ministry of Infrastructure and Transport. The meeting greenlit the final technical adjustments and economic feasibility of the entire plan, clearing the path for the operational phase to commence. Roma will present the executive project shortly and break ground in spring, with construction targeted for completion by 2030 in time for Euro 2032, scheduled to take place in Italy and Turkey. The club will continue playing at the Stadio Olimpico until the new ground is ready. The new stadium will hold 60,000 seats, with roughly a third dedicated to the new Curva Sud, designed in the style of Borussia Dortmund's Die Gelbe Wand. The project incorporates a substantial new park, a club museum and store. According to QuiFinanza, the stadium itself will cost approximately €600 million, while the entire project is priced at €1.37 billion. The Friedkin Group and its partners will finance the scheme entirely through their own capital, a construction loan, a project bond and a VAT facility. The final deadline for completion falls roughly one year before Euro 2032 kicks off. The stadium's relocation to a different part of the city carries significant urban planning implications for Rome.

Cult of CalcioRead original →
Roma's new Pietralata stadium: the final steps before groundbreaking in March 2027
Club News● AI
2h ago

Roma's new Pietralata stadium: the final steps before groundbreaking in March 2027

AS Roma's new stadium at Pietralata has cleared its biggest hurdle. The Services Conference concluded positively and the single authorization was signed, closing the main approval phase of the project. The groundbreaking is targeted for March 2027, but several technical and administrative steps remain before construction can begin. Crucially, the dynamic has shifted: the question is no longer whether the stadium will be built, but whether all necessary procedures can be completed to make it a functioning construction site. The first phase involves detailed design. The approved executive project must be further developed to incorporate all requirements that emerged during the Services Conference, including archaeology, environment, traffic and public works provisions. This stage is expected to take three to four months. Parallel verification and validation activities must also proceed ahead of actual construction work. Significantly, much of the process will not rest solely with Roma. A central step is a public tender for the concession—which covers detailed design, construction and management of the facility plus surface rights over municipal areas. This is not a private procurement where the club freely selects a contractor; the procedure must follow public-private partnership rules. Roma, as project promoter, begins from a particular position and may exercise rights provided by regulations within the procedure. The club must complete design work and prepare the construction phase while Rome's municipal administration handles project verification, the public concession procedure and area procedures. These steps can largely run in parallel. Additionally, procedures for expropriating private portions necessary for the project—now possible following the public utility declaration—must be finalized, with costs borne by the concessionaire. Archaeological activities required by the Archaeological Superintendent must also continue. The final phase involves concession award, agreement, guarantees, creation of surface rights and area handover. Only when all these elements are in place can the project become a functioning construction site. The March 2027 target remains realistic but not automatic; meeting it requires Roma and the administration to run all procedures simultaneously without significant delays.

GialloRossi.netRead original →
Roma to honour Alba Audace with third kit for 2027-28 centenary season
Club News● AI
2h ago

Roma to honour Alba Audace with third kit for 2027-28 centenary season

AS Roma are preparing third-kit designs for their centenary campaign, with details emerging of a tribute to Alba Audace, one of three clubs that merged to form the giallorossi. The 2027-28 third kit will feature a white base with dark green details and carry the ASR acronym badge already used in the current season, according to Footyheadlines. Adidas will continue as kit supplier through the centenary year, with the design honouring Alba Audace's heritage without reproducing its original crest. The full presentation remains some way off, but the leaked concept signals a clear intent to mark the approach to 22 July 2027—the club's 100th anniversary—with historical resonance. The kit details offer the first concrete indication of how Roma plan to celebrate the milestone season.

Feedback